Building
  • Electrical, Mechanical and Plumbing permit final inspections must be approved.
  • Site address installed per the 911 ordinances.
  • The grade away from the foundation shall fall a minimum of 6 inches within the first 10 feet from the foundation.
  • Required steps, handrails, guardrails and landings shall be installed.
  • All smoke detectors shall be operational.
  • Final building inspection approval and all re-inspection fees, if any, shall be paid.
Electrical
  • Breaker panel directory must be complete in detail and accuracy.
  • All electrical installation must be completed including all covers, plates and caps for safety from shock.
  • All light fixtures with bulbs; need to be installed for testing.
Mechanical
  • A Mechanical permit secured by a licensed contractor for propane gas must pass its final inspection.
  • Furnace, ductwork and register grills must be installed. Any fireplaces must be operable.
Plumbing
  • All plumbing fixtures must be installed and working.
  • Final septic and water approvals by the appropriate health department.