When do I need inspections?
The type and number of inspections depend on the project. The following are required in Clinton County:
-
Footing and setback
-
Foundation inspection before the backfill
-
Framing and rough-in
-
Insulation
-
Electrical rough-in
-
Sewer and water service lines
-
Plumbing groundwork
-
Plumbing rough-in
-
Final inspection includes: heating, electrical, plumbing, house numbers, any safety items confirmed, etc.
Some of these inspections can be combined. Inspection requests called in before 4 p.m. will be scheduled for the following day. When calling for inspection, please have the following information ready: Name of permit holder, building address, township and permit number. Call 989-224-5183 to schedule all inspections.