The Drain Commissioner is assessing $60,000 over 3 years.
The #870 Thome & Wieber was last assessed in 2021.
Work Completed
• Problem report response in 2022, bank erosion
• Culvert replacement at Centerline Road in 2022
• Engineering study and recommendations for East Branch in 2022 (C2AE)
• Cattail spraying in 2022 (LVM)
• Channel realignment and stabilization in 2022 (Lloyd’s Excavating)
• Meetings to discuss engineering alternatives and recommendations in 2023
• Planned work to install relief drain pipe in 2023